Planned Maintenance In Progress

Updated a few seconds ago

0

Active Incidents

0

Upcoming Maintenances

14

Days Since Last Incident

Plant MaintenancePlanned Maintenance

Description

Infrastructure that Pioneer Communications utilizes to deliver your service is scheduled for routine maintenance. From time to time this must be done to continue to deliver the highest quality of service. Services in the following areas may be impacted. Sublette

Components

Internet

Locations

Sublette

Schedule

July 25, 2022 9:00AM - July 28, 2022 5:00PM CDT



July 25, 2022 6:56PM CDT
[Update] Pioneer Communications will continue to preform maintenance on Tuesday 7/26 and Wednesday 7/27.

July 25, 2022 6:54PM CDT
[Update] Maintenance started this morning in Sublette. Pioneer Communications will continue with the maintenence Tuesday morning.

Internet

Service Disruption

StreamTV

Service Disruption

Telephone

Operational

WiFi 360

Operational

DNS

Operational

Email (pld.com)

Operational

Hosted PBX

Operational

Special Access

Operational

History (Last 14 days)

Network MaintenancePlanned Maintenance

Description

Pioneer Communications will be performing maintenance on equipment that carries our voice traffic . From time to time we must do this to be able to continue to deliver the highest quality of service. No outages are expected but there is a chance that 911 and long distance calling might be prohibited. We will notify you when maintenance is complete.


Components

Telephone, Special Access


Locations

Big Bow, Coolidge, Deerfield, Garden City, Hickok, Hugoton, Johnson, Kendall, Lakin, Moscow, Richfield, Rolla, Ryus, Satanta, Syracuse, Ulysses, Rural Grant County, Rural Finney County, Rural Hamilton County, Rural Haskell County, Rural Kearny County, Rural Morton County, Rural Seward County, Rural Stanton County, Rural Stevens County, Network Operations Center


Schedule

September 30, 2022 12:01AM - September 30, 2022 5:00AM CDT



September 30, 2022 1:01AM CDT
[Update] Maintenance complete.

September 30, 2022 1:00AM CDT
[Update] Maintenance is complete.

September 30, 2022 12:01AM CDT
[Update] Scheduled maintenance is starting.

Incident Status

Operational


Components

Internet, Telephone, Special Access


Locations

Rural Hamilton County, Network Operations Center




September 23, 2022 1:03AM CDT
[Resolved] Fiber has been repaired. All services restored.

September 22, 2022 2:45PM CDT
[Identified] Fiber crews are onsite exposing damaged fiber. ETR is 7:00 PM CST.

September 22, 2022 10:01AM CDT
[Identified] We have identified a cut fiber between Manter and Coolidge. Crews are in route to repair. We will post further updates as they become available.